Inside Resources - Brookby manufactured sand plant hitting target

SOURCE INSIDE RESOURCES, COLLIN WILLISCROFT, WED FEB 5 2025

Brookby Quarries' manufactured sand plant that was commissioned last July can now produce 300,000 tonnes of product a year in accordance with its client specification requirements.

A second stage - which would increase that to 500,000 tonnes annually - could be up and running in six months, if demand requires.

Managing director Steve Riddell says the challenge has been getting the required sales volume capability without altering the specification, which was achieved in 2023.

"The rest of the time it was about getting the new processing equipment on site that gave us the production capabilities for our clients. Then, when we had the capacity, making sure we did not alter the specification.

"Achieving that volume without altering the specification has been the technical challenge that we've dealt with in the past six months, which we successfully resolved late last year."

Logistics

Getting large pieces of equipment on-site to meet the production capacity required by the market has involved long lead times, with the equipment coming from Ireland, the US and India.

Riddell gave the example of a Powerscreen portable crusher and cone that is capable of processing 700-800 tonnes of rock an hour. It had to come from Belfast in Northern Ireland and it took about two years from the initial order to being commissioned and operating on the site.

There was also a roll-on effect from Covid, which tightened and slowed supply.

That type of issue is not expected to be a problem with stage two, which he says is basically sitting at an amber light, ready to go and only subject to the market needing more sand.

Stage 2, if needed, could be commissioned in about six months, subject to availability of equipment - which is known to be available at present.

He estimates about $12 million has been spent on the project so far. The second stage would require a further $4 million.

The operation uses premium Brookby greywacke, and the sand produced is currently sold into the Auckland region.

Equipment

The operation utilises primary and tertiary crushers, and vibrating screens to take the raw aggregate input feed of a maximum size of 750 mm and breaks that down to sand-sized particles.

After being downsized to a product that's 0-3.1 mm, it's then passed through an aggregate washing system to clean the product and remove any remaining impurities.

The aggregate washing process involves large clarifiers and storage capacity for about a million litres of recirculating water, which is recycled once it has been cleaned for reuse.

The byproduct is then passed through a large filter press that removes the super fines from the slurry before recirculating about 600 cubic metres of clean water per hour back into the washing process.

Knowledge, power

The plant was commissioned in-house using the company's own technical knowledge with the added support of key concrete clients.

A significant component of the commissioning involved completing the installation and commissioning a new 5 MW mains power supply in May last year.

Previously, the Brookby operation had been using a combination of mains power supply and diesel generators to produce 2.2 MW of electricity.

However, the diesel supply has now been mothballed and will act as a back-up for the main plant in the event of a mains power outage.

Other diesel-powered plant onsite is being converted to the new mains power supply.

Previous
Previous

Inside Resources - Brookby expansion underway

Next
Next

Inside Resources - Brookby expansion approved